Role
Project Executive
Company
Layton Construction
Industry
Healthcare
Value
$85 Million
Delivery
Early Design Involvement
Jurisdiction
OSHPD / HCAI
Multi-phase renovations on every floor of (2) patient towers to allow for the installation of concrete shear walls going from building foundation to roof - to make existing buildings SPC-4D compliant. Plans also include temporary kitchen, 5,000 SF building expansion for new kitchen, and (11) underground tanks for NPC-5 compliance.